Appendix B
Service Monitoring
The following describes what needs to be done for every conveyor in the system.
Initial measuring data
Gap, chain-beam, top
(Gap_top)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Gap_top
Thickness of chain top (Chain_top)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Chain_top
Gap, chain-side plate, idler end (Gap_idler)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Gap_idler
Thickness of tab (Chain_tab)